|
THE NATURAL GAS DEVELOPMENT PROJECT IN THE JDA
Block A-18
CAKERAWALA GAS DEVELOPMENT
PROJECT
The Cakerawala Gas Field is located offshore in the lower part of the Gulf of Thailand approximately 150 km Northeast to Kota Bharu and 160 km East of Narathiwat in water-depth of about 60 meters in contract area of Block A-18 in the Joint Development Area.
The Cakerawala field development project consists of three Wellhead Platforms (CKA, CKB and CKC), Central Processing Platform & Living Quarters (CKP), Riser Compressor Platform (CKR) and FSO (Puteri Cakerawala). Initial processed gas at a rate of 390 mmscf/d will be delivered to the Buyers sales pipeline originating on riser platform.
The field is developed with the following facilities (as shown in pictures below): |
|
 |
 |
The construction Contract for the facilities of Cakerawala Gas Development Project was signed in March 2000. |
 |
The Cakerawala Complex was successfully installed offshore in June 2002. |
 |
Cakerawala Gas Field Development Facilities are completed as per Gas Sales Agreement obligations (390 MMscf/d) in September 2002. |
 |
Engineering, Procurement and Construction (EPC) of pipeline (TTM) contract awarded in April 2003. |
 |
The Operational Acceptance of Cakerawala Facilities was issued in July 2003. |
 |
In December 2004, the MTJA and the Contractors of Block A-18 signed the Supplementary Agreement to sale additional 400 MMscfd to Buyers (PTT and Petronas). The total Daily Contract Quantity (DCQ) from Block A-18 is 790 MMscf/d. Additional volume is sold to the new Northern 42-inch pipeline connecting to Arthit PLEM in the Gulf of Thailand. |
 |
Commencement of first JDA gas (Phase 1) production from Cakerawala Gas Field, Block A-18 in January 2005. |
 |
Block A-18 first condensate lifting from FSO "Puteri Cakerawala" on 29 June 2005. |
 |
Commenced Phase 2 Development in February 2006. |
 |
Phase 2 facilities were installed in quarter 3 and quarter 4 of 2007. |
 |
Phase 2 facilities were ready to export 790 MMscfd of gas in April 2008. |
 |
The Northern 42-inch gas pipeline was successfully installed by TTM in October 2008. |
 |
Natural gas was first introduced into the 42-inch Northern pipeline in November 2008. |
 |
Block A-18 Gas Sales achieved first ever daily delivery exceeding 1 Billion cubic feet per day (Bscf/d) in September 2009. |
 |
Block A-18 Condensate sales achieved 10 million barrels in May 2010. |