CHRONICLE
   
15 January 2007
Appointment of the fifth Chief Executive Officer of MTJA, Mr. Abd Halim Che Abas to continue the remaining term for Malaysia. (January 2007 - September 2008).
   
31 January 2007
CPOC awarded the EPCC CPP Topside contract for Block B-17 & C-19 Gas Field Development Project to SOME Pte. Ltd.
 
   
June 2007
BMA-CKR pipe began laying.
 
   
July 2007
CPOC awarded 4 wellhead platforms to PILFAB Sdn. Bhd. and 8-legged CPP jacket to Malaysia Marine and Heavy Engineering Sdn. Bhd.
 
   
14 July 2007
Bumi-A platform (BMA) was loaded out and transported to install at site.
   
16 July 2007
Suriya-A platform (SYA) was loaded out and transported to install at site.
   
4 August 2007
Bulan-A platform (BLA) was loaded out and transported to install at site.
   
October-November 2007
Buyer's 42" Riser & Emergency Shutdown Valves (ESDV) Installation on CKR for BMA, SYA and BLA.
   
October 2007
Carigali Hess successfully tested the High Pressure High Temperature (HPHT) reservoir in Bumi Gas Field.
   
22 December 2007
Mechanical completion of the Phase 2 facilities for Block A-18.
   
31 January 2008
CPOC awarded the Leased Floating Storage and Offloading Facilities (FSO) "Ratu Songkhla" to M3NERGY Berhad for 16 years lease period.
   
24 June 2008
First wellhead platform (MDA) for Block B-17 sail away to JDA.
   
4 August 2008
MDA Platform for Block B-17 completely installed.
   
1 October 2008
Appointment of the sixth Chief executive Officer of MTJA, Mr. Suriyan Aphiraksatyakul from Thailand for a 4-year term. (2008-2012).
   
1 November 2008
JKA for Block B-17 completely installed.
   
19 November 2008
MDB & MDC topside for Block B-17 load out on Teras 281.
   
23 November 2008
MDLQ Deck for Block B-17 load out.
   
December 2008
The 4 wellhead platform (MDA, MDB, MDC and JKA) for Block B-17 were completely installed in August, November and December, respectively.
   
8 January 2009
The Central Production Platform (CPP) 8-legged jacket for Block B-17 was installed at offshore location.
   
11 June 2009
Muda Living Quarters Building load out and sail away.
   
30 July 2009
Muda Production Platform (MDPP) load out and sail away.
   
01 October 2009
Appointments of the fourth Malaysian Co-Chairman of the MTJA, Tan Sri Khalid Ramli.
Appointments of the fourth Thai Co-Chairman of the MTJA, Mr. Nopadon Mantajit.
   
08 December 2009
Block B-17 gas was registered.
   
April 2010
First Block B-17 Muda condensate lifted with 296,880 barrels.
   
May 2010
Block A-18 Cakerawala condensate sales achieved 10 million barrels.
   
 