CHRONICLE |
| |
|
15 January 2007
Appointment of the fifth Chief Executive Officer of MTJA, Mr. Abd Halim Che Abas to continue the remaining term for Malaysia. (January 2007 - September 2008). |
 |
| |
|
31 January 2007
CPOC awarded the EPCC CPP Topside contract for Block B-17 & C-19 Gas Field Development Project to SOME Pte. Ltd. |
|
| |
|
June 2007 BMA-CKR pipe began laying. |
|
| |
|
July 2007 CPOC awarded 4 wellhead platforms to PILFAB Sdn. Bhd. and 8-legged CPP jacket to Malaysia Marine and Heavy Engineering Sdn. Bhd. |
|
| |
|
14 July 2007
Bumi-A platform (BMA) was loaded out and transported to install at site.
|
| |
|
16 July 2007
Suriya-A platform (SYA) was loaded out and transported to install at site.
|
| |
|
4 August 2007
Bulan-A platform (BLA) was loaded out and transported to install at site.
|
| |
|
October-November 2007
Buyer's 42" Riser & Emergency Shutdown Valves (ESDV) Installation on CKR for BMA, SYA and BLA.
 |
| |
|
October 2007 Carigali Hess successfully tested the High Pressure High Temperature (HPHT) reservoir in Bumi Gas Field.
|
| |
|
22 December 2007
Mechanical completion of the Phase 2 facilities for Block A-18.
|
| |
|
31 January 2008
CPOC awarded the Leased Floating Storage and Offloading Facilities (FSO) "Ratu Songkhla" to M3NERGY Berhad for 16 years lease period.
|
| |
|
24 June 2008
First wellhead platform (MDA) for Block B-17 sail away to JDA.
|
| |
|
4 August 2008
MDA Platform for Block B-17 completely installed.
 |
| |
|
1 October 2008
Appointment of the sixth Chief executive Officer of MTJA, Mr. Suriyan Aphiraksatyakul from Thailand for a 4-year term. (2008-2012).
|
|
| |
|
1 November 2008
JKA for Block B-17 completely installed.
|
|
| |
|
19 November 2008
MDB & MDC topside for Block B-17 load out on Teras 281.
|
| |
|
23 November 2008
MDLQ Deck for Block B-17 load out.
|
| |
|
December 2008
The 4 wellhead platform (MDA, MDB, MDC and JKA) for Block B-17 were completely installed in August, November and December, respectively.
|
| |
|
8 January 2009
The Central Production Platform (CPP) 8-legged jacket for Block B-17 was installed at offshore location.
|
| |
|
11 June 2009
Muda Living Quarters Building load out and sail away.
|
| |
|
30 July 2009
Muda Production Platform (MDPP) load out and sail away.
|
| |
|
01 October 2009
Appointments of the fourth Malaysian Co-Chairman of the MTJA, Tan Sri Khalid Ramli. Appointments of the fourth Thai Co-Chairman of the MTJA, Mr. Nopadon Mantajit.
|
| |
|
08 December 2009
Block B-17 gas was registered.
|
| |
|
April 2010
First Block B-17 Muda condensate lifted with 296,880 barrels.
|
| |
|
May 2010
Block A-18 Cakerawala condensate sales achieved 10 million barrels.
|
| |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|