1995 - 1998
29 exploration and appraisal wells were drilled in the JDA by CTOC and CPOC resulting in the discovery of 15 gas fields. Total accumulative exploration investment is about USD 364 million.
(click image to view
larger image)
|
| |
|
22 April 1998
Two Heads of Agreements (HOA) of the Gas Sales Agreement (GSA) for the supply of Gas from JDA Block A-18 and from JDA Blocks B-17 & C-19 were signed in Songkhla between MTJA & the Contractors of the respective blocks and PTT & PETRONAS.  |
| |
|
30 October 1999
Gas Sales Agreement (GSA) for the supply of Gas from Block A-18 of the JDA was signed in Alor Setar between MTJA & the Contractors of Block A-18 (the Sellers) and PTT & PETRONAS (the Buyers).
|
|
|
|
| |
|
January 2000
Appointments of third Malaysian Co-Chairman of MTJA, Tan Sri Abu Talib Othman. |
 |
| |
|
February & March 2000
Trans Thai-Malaysia (Thailand) Limited (TTM) was incorporated.  |
| |
|
8 March 2000
CTOC awarded EPC contract for the engineering, fabrication and installation of the Cakerawala Gas Field production platform and facilities to the Technip-Samsung-Saipem Consortium, with target of completion in 28 months in order to deliver natural gas (1st phase) to the Buyers by the end of June 2002.  |
|
|
1 October 2000
Appointment of the third Chief executive Officer of MTJA, Dr. Kurujit Nakorntha from Thailand for a 4-year term. (October 2000 - September 2004). |
 |
|
|
May 2001
Installation of the first Platform Jacket for the Cakerawala Gas Field Development Project in the JDA Block A-18 was completed.  |
|
|
20 April 2002
Exploration period for Block A-18, B-17 and C-19 has expired, current Contractor retain the Gas Holding Area in these blocks. An areas of approximately 3,475 sq.km were relinquished to MTJA as a new block in the JDA.
(click image to view
larger image)
|
|
|
22 June 2002
Inauguration Ceremony of CKP-Living Quarters at Cakerawala Gas Field Production Facilities in Joint Development Area.

|
| |
|
September 2002
Cakerawala Production Facilities Offshore Block A-18 JDA are completed, installed and commissioned with 19 development wells.
 |
|
|
July 2003
The Operational Acceptance of Cakerawala Facilities was issued. |
|
| |
|
30 September 2004
Signing of Production Sharing Contract (PSC) between MTJA and Contractors for its right to explore and exploit petroleum in Block B-17-01 of JDA.
|
|
| |
|
1 October 2004
Appointment of the fourth Chief executive Officer of MTJA, Mr. Zarei Mohamed from Malaysia for a 4-year term. (October 2004 - October 2006; deceased on 17 October 2006).
|
|
| |
|
December 2004
Completion of TTM receiving facilities and offshore pipeline system.
|
| |
|
23 December 2004
MTJA and its Contractors of Block A-18 (Sellers) and PTT & PETRONAS (Buyers) signed the Supplement Agreement to the GSA.
 |
| |
|
2 January 2005
Start-up of TTM offshore pipeline and onshore receiving facilities. |
|
|
| |
|
20 February 2005
The JDA gas successfully delivered to Malaysia border into Peninsular Gas Utilisation (PGU) system.  |
| |
|
21 February 2005
Teknologi Tenaga Perlis Corporation (TTPC) started consuming JDA gas.  |
| |
|
16 June 2005
PTT Public Company Ltd. signed a Gas Sales Agreement (GSA) with MTJA, PCJDA Ltd. and PTTEP International Ltd. in Bangkok for gas from Blocks B-17 & C-19 and Block B-17-01. |
| |
|
29 June 2005
The first condensate lifting from FSO "Puteri Cakerawala".  |
|
|
|
|
|
|
|
|
|
|
|
|